Sunday, March 4, 2012

Hey it's still winter up here!!!




Weather reports were deceiving, night time temps were expected to be 28-30 degrees, high enough that we can camp out without too much difficulty from cold temps. The actual weather though was a good storm that brought about 6 to 10 inches of new snow to the HL area. Grayling got 13 inches and Gaylord reported up to 17 inches of snow. We were driving up and just north of Harrison road conditions really switched , one moment wet roads from constant rain then the next a good covering of slush. By the time we hit exit 189 it was snow pack.













These pictures are from the morning after. We left snow pants and such home ( who needs snow clothes when Spring is just around the corner??) Power outages were common, we missed the tree falling on our power by about 4 cabins so we had electric.























Going home on Saturday the roads were mostly plowed but COLD temps were coming and we left a little early to make sure we had good driving and no ice slicks. Not much work done, we played in the snow, made lunch and such. Took time to enjoy the place. The kids are getting good at hitting targets with the bb gun.













Dogs are looking for the ball, it sank into the snow and Hunter is digging it out. Snow was at least 24 inches deep and dogs were not running away today!! We dugout the driveway to get into the drive on Friday night but paid to have it plowed out so when it froze it was cleaned out if it doesn't melt by the time we get up again.

Saturday, February 18, 2012

Feb. 18th


Futon moved to loft "where it's warmer" in Winter. The mutts need a doghouse for the cold, they were troopers while we went to the store and eat lunch.




Hung some drywall on stairway wall. Noticed we goofed on the electric wiring and need to get it buried in the wall.

Another decent day weatherwise, we got there bout noon and got a fire started to warm up the house. The breeze off the lake pretty much killed any wild ideas of hanging the blue insulation outdoors. I keep forgetting it is winter in Michigan. Ben wanted to shoot his bb gun but I didn't want to stay outside so we set up the targets upstairs. He shoots high and to the left, need to work on that.

Saturday, February 4, 2012

Feb. 4 36 degrees?????

Worked on the wall for the stairs today. Had to put in some of the ceiling carsiding to align with the wall. This can get drywalled and ready to go. Now we can run electric up through the wall for the upstairs stuff.

Hunter was chilling upstairs, Hank had been sleeping too but jumped up when I grabbed the camera. Upstairs temps were easily in the high 70's with the woodstove.





Monday, January 30, 2012

January 29th

Weather was typical wintertime, about 27 degrees for highs. We drove up kinda late but figured we needed to spend some time on the floor project. Built the fire and went to work....

Laid 2 sheets down and got them all glued and screwed. We have one more to go then second floor will be done. After that there are some small pieces needed to be cut for the front wall section. We saved them for last to use scraps for them.

Not much roof snow, I think the breeze off lake helps blow it off for us. Driveway was deep enough we should have it plowed but rain is in the forecast for the week.

Window opening are 22x 36 for the back wall. Need to get pricing on them.

We are under $12,000 on the mortgage, just got statement.

Thursday, January 12, 2012

January 7th Bonus Day

Well temps stayed moderate and we spent the day at the cabin. Put in 2.5 sheets of OSB. Next week temps are looking to not get out of the 20's and that is a tad cold for working.

We also went to Home Depot and bought more supplies, should have enough 2x4's to do walls upstairs now.

There are 3 sheets to lay and the floor will be one, unfortunately all 3 need major cutting. All sheets have been custom cuts due to the "squareness" of the old building.

Kids are excited that there will be a bedroom upstairs for this years camping season.

Sunday, January 1, 2012

New years eve- "It is done...." mostly

Finally got all the stairs installed. NO MORE STAIR REPORTS!!! Hank was freaked out on going up the stairs and had a hard time getting up to the loft. On the right side of pix you can also see the flooring was put in and the wall that will be installed for that side. We got 5 sheets of OSB to lay down then the floor will be done upstairs.


The stars indicate what we are taking out next spring. Sitting in the loft there is no good visibility looking outside. These windows will not open just glass for view.


Monday, December 26, 2011

Dec. 26th


Ceiling fan getting installed. We need to get wall built on right side of stairs so wire can be worked down to the switch box.


Wow 40 degrees today. Nice day to be up north, blue skies too. Ben tried out his pellet gun out back. Woodstove kept place very toasty.


I'm sick of posting pictures of the stairs, but we got to the last two and then they will all be installed. Need table saw to cut two risers and then we will be done.


Anyways enough steps were done that kids and dogs are going upstairs. Hank was totally freaked about being upstairs, funny since he climbs trees at the drop of a squirrel.


Hunter was sleeping next to me while I sat in chair. We built a safety rail on end and need to fill it in a bit to keep everyone from leaning over the edge. First step is a doosie.....